Lightning Protection Inspection

A lightning protection inspection template for a structural system, written around what actually fails. Rarely the conductor. Usually a bond that came off during roof works and never went back, which is invisible from the ground and only shows when the readings are taken.

  • Thirty-five checks plus resistance readings compared with last time
  • The roof walked against the original drawing, not against memory
  • Every test joint opened, because a painted joint was never tested
  • A count of roof additions found unbonded, reported to roof access
lightning-protection-inspection.xlsx

Lightning Protection Inspection

One system, one inspection

Roof works since the last inspection
Because new plant rarely gets bonded in
Original design and drawing reference
What the roof is being walked against
Design limit and test point schedule
The figure each reading is judged on
Inspected by, name and competence
Named, with the test instrument and its calibration
#Air termination and roof itemSoundDefectN/A
1New plant installed since last inspection bonded in
2Solar array and its frame bonded where present
3Test joints accessible, identified and operable
+ thirty-two more checks across three sections, covering twelve air termination lines from mesh spacing and fixings to expansion joint provision and whether the protected volume still covers what has been added, twelve down conductor lines including bonds to structural steel, incoming services and curtain walling, and eleven electrode and surge lines from pit access and enhancing compound to staged coordination, plus a resistance table that carries the last reading alongside this one, a defects table graded Critical, Major or Minor, and a rolling Test Log tab

The document you will get. Download for the full, editable file.

Who this lightning protection inspection is for

Four people are involved here, and three of them have no idea the system exists.

  • The test engineer

    Sections 2 and 4 are where the real findings are. One is a walk against a drawing rather than a look at a roof, the other is a comparison against the last set of readings rather than against a limit.

  • Facilities or estates

    The unbonded additions count is yours, and it is not an electrical problem. Every one of them was installed by somebody who did not know the system was there, which makes it a permit and handover issue.

  • Whoever specifies roof plant

    You are the reason this count is never zero. A new condenser frame or cradle track is a structural addition to a protected volume, and bonding it is part of installing it rather than something discovered a year later.

  • The responsible person for the building

    Surge indicators. A device reading operated means the building took a strike that nobody logged, and the protection it provided is spent until somebody replaces it.

Which section matters the most in your sector

The physics is the same everywhere. What changes is how much gets added to the roof, how exposed the structure is, and what inside the building cannot tolerate a transient.

What a lightning protection inspection should contain

A lightning protection inspection is the recorded visual inspection and resistance testing of a structural lightning protection system. It walks the air termination network against the design drawing, opens the test joints, measures each earth electrode, compares the readings with the last set, and checks whether surge devices have already operated.

A. Fields specific to a lightning protection inspection

FieldWhat goes in itWhy it earns its place
Roof works since the last inspectionWhat was done, by whom, and whenThe first field because it predicts the findings. New plant, cable trays, aerials and solar arrays all change the protected volume, and they are installed by people who have no reason to know the system is there.
Original design and drawing referenceWhat the roof is being walked againstWithout it this becomes a look at a roof rather than a comparison. The whole method depends on knowing what was supposed to be there, because absences do not announce themselves.
All roof metalwork bondedHandrails, walkways, plant, cradle tracksWritten as a sweep rather than a list because the list changes. Anything conductive and substantial on a roof inside the protected volume needs connecting, and the common finding is a plant platform sitting above the network with no link to it.
Protected volume still adequateFor everything added since installationA separate question from whether things are bonded. A mast or a tall unit added later can stand outside the volume the original design produced, which is a design problem rather than a maintenance one.
Test joints accessible and operableOpened, not inspected from outsideThe check that distinguishes a real inspection from a plausible one. A joint painted over or seized was never tested, and a record saying otherwise was taken from the outside of a clamp.
No conductor cut, disconnected or shortenedChecked along the full runConductors get cut for access during other work, and the two ends are rarely rejoined by whoever cut them. From any distance the run still looks continuous.
This reading against the last readingBoth, side by side, with the changeThe pair of columns the document is built on. A single reading answers whether the system passes today; two readings answer whether it is getting worse, which is the only early warning this system gives.
Combined system resistanceAgainst the design limitThe headline figure and the one most likely to be reported alone. It can sit comfortably within limit while an individual electrode is failing, which is why individual readings are recorded as well.
Electrodes disturbed by landscapingChecked specifically, with pits clear and liddedEarth electrodes lose to groundworks more often than to corrosion. A pit paved over, buried under planting or dug through is a test point that can no longer be measured or maintained.
Surge device indicatorsHealthy or operated, read at every deviceSurge devices are consumable by design. An operated indicator means the building has already taken a transient, the device did its job, and the protection is now spent until it is replaced.
Evidence of a strike since last inspectionRecorded, including what prompted the suspicionMost strikes on a protected building pass without anybody noticing, which is the system working. The indicators and any pitting at terminations are the only trace, and they are worth recording as history.
Roof additions found unbondedA count, reported to whoever controls roof accessThe figure to escalate rather than fix quietly. Each one represents an installation that happened without reference to the system, so the fix is a permit and handover change rather than another bond.

If you cut this down, keep the previous reading column and the unbonded additions count. Both describe change rather than condition, which is what this system gives you instead of symptoms. A lightning protection system has no operating state to observe: it does nothing at all between strikes, it makes no noise, and a severed down conductor looks exactly like an intact one from ground level. The only two things that reveal its actual health are a measurement compared with the previous measurement, and a comparison of the roof against its drawing. Drop the previous reading and every inspection becomes an independent pass or fail, which means a connection degrading steadily over three inspections reads as three passes and then, without warning, a failure. Drop the unbonded count and you still fix the bonds you find, but you lose the only evidence that the real problem is upstream: a roof access and handover process that keeps letting people install metalwork on a protected roof without anybody telling them the system exists.

B. What it looks like filled in

One test point across four annual inspections, from the Test Log tab. The design limit is 10 ohms.

InspectionReading, ohmsLimitWithin limitChange since last
20243.110YesFirst reading
20254.410YesUp 42 percent
20267.910YesUp 80 percent
202711.210NoUp 42 percent

Three passes, then a failure, and the failure was visible two inspections earlier. Every one of the first three readings was inside the design limit and every one was recorded as a pass, which is correct and also useless on its own. Read down the last column instead and the electrode was deteriorating from the second inspection onward, rising by roughly half again and then nearly doubling while still reporting as compliant. By the time it crossed the limit it had been getting worse for three years, and the remedial work it eventually needed was considerably larger than the work it would have needed in 2025. This is the entire argument for carrying the last reading beside the new one on the sheet: the limit tells you whether the system is acceptable today, and only the comparison tells you whether it will be acceptable next time.

Download the lightning protection inspection template

Word to adapt the checks to your own system and design standard, Excel for the resistance table that carries the last reading beside this one, the defect grading and the Test Log tab that makes the trend visible, PDF for the copy that goes up to the roof. Free, and yours to rebrand.

Get the template

How do you inspect a lightning protection system?

One system, one inspection, and it starts with a drawing rather than a roof. Six steps.

  1. Find out what has changed up there since last time

    Building and structure, the original design and drawing reference, the design standard, the test point schedule and design limit, the maintenance provider, the test instrument and its calibration, and who is carrying this out. Then the field that predicts most of the findings: what roof works have taken place since the last inspection, because new plant, trays, aerials and arrays are installed with no reference to this system.

  2. Walk the roof against the drawing, not against the roof

    Twelve checks. Air terminals, rods and finials secure, mesh conductors continuous, correctly spaced and clipped, nothing slack, kinked or lifted, fixings intact and not pulled from the substrate. Then the bonding sweep: all roof metalwork, new plant since the last visit, solar arrays and their frames, aerials, dishes and masts. Rooflights and penetrations within the protected volume, joints sound with no dissimilar metal corrosion, expansion joint provision, and whether the protected volume still covers what has been added.

  3. Follow every down conductor to earth, opening the joints

    Twelve checks covering conductors complete from roof to earth, routes direct without unnecessary loops or sharp bends, protection where they pass through public areas, fixings intact along the run, and test joints accessible, identified and operable. Then the bonds: structural steel and reinforcement, incoming water, gas and electrical earth, equipotential bonding at entry points, nothing cut or shortened, cladding and curtain walling, labels at test points, and separation distance from other services.

  4. Take the readings, and write the last ones next to them

    Record each test point with its electrode type, this reading, the last reading, the change between them, the limit and whether it passes. The comparison is the point. A reading that has risen sharply while staying inside the limit is a connection degrading, and it is the only advance warning this system produces.

  5. Check the electrodes and read the surge devices

    Eleven checks. Electrodes accessible with pits clear and lidded, connections sound and free of corrosion, nothing disturbed by landscaping or excavation, enhancing compound intact, combined resistance within the design limit and individual readings recorded. Then surge protective devices present at service entries, indicators showing healthy rather than operated, protection at data and telecom entries, devices replaced where they have operated, and coordination between stages.

  6. Grade the defects, then escalate what should never have happened

    Mark each defect Critical, Major or Minor. A severed down conductor or a reading beyond the limit is Critical, because the system is not providing the protection the building is assumed to have. Then the result: test points within limit, combined resistance, readings risen since last time, surge devices needing replacement, evidence of a strike, and the count of roof additions found unbonded, which goes to whoever controls roof access rather than into an electrical report.

A certificate in a folder cannot tell you the reading has doubled. See how inspection management holds readings, trends and the roof additions nobody declared.
See inspection management

Reading against the limit versus reading against last time

Every inspection does the first of these. The second costs nothing extra and is where almost all the useful information is.

AspectReading against the limitReading against last time
What it answersIs the system acceptable todayIs it on its way to not being
What it producesA pass or a failA direction, and a rough date
When a failing connection showsThe year it crosses the limitTwo or three years earlier
What it needsThis reading and a number from the designThe last reading, kept somewhere findable
How a degrading electrode readsPass, pass, pass, failUp 42, up 80, and act before the fail
What the remedial work looks likeUrgent, and larger than it needed to bePlanned, and smaller

A lightning protection system gives almost no symptoms, which makes the trend the only diagnostic it has. Consider what the alternatives would be. The system does nothing between strikes, so there is no performance to degrade and nobody notices a change in behavior. It is mostly out of sight, on a roof or buried, so visual deterioration goes unseen for years. And the failures that matter most are absences rather than faults: a bond removed, a conductor cut, an electrode dug through. None of those produce an alarm, a noise or a complaint. What is left is measurement, and a single measurement compared against a design limit throws away most of what the measurement knows. An electrode rising from three ohms to eight has lost most of its margin and is telling you so clearly, but judged against a limit of ten it is simply another pass, filed identically to the one before it. Keeping the previous reading on the same row converts a compliance check into a condition monitor, at no extra cost in time or equipment, and it is the difference between planning a repair and discovering one.

When the template starts to feel limiting

One building with a certificate works. A portfolio, inspected annually by different engineers, is where it stops.

  • Last year is reading is in last year is report

    The comparison only works if the previous figure is to hand. In practice it is in a PDF in a folder, so the engineer standing at the test point records a pass against the limit and the trend is never calculated.

  • Nothing connects roof works to this system

    A contractor installs a condenser frame in March and the lightning protection inspection happens in October. Between those dates the system is incomplete and nobody in the building is aware of it.

  • An operated surge device waits a year

    The indicator changed the night of the strike. It gets read at the next annual inspection, which means the building can spend most of a year with spent protection and no record of why.

  • Unbonded additions never reach the people causing them

    The count sits in an electrical report sent to whoever commissioned the inspection. The roof access process that let the installation happen is owned by somebody else entirely, and nothing routes it there.

What running this in Facilio looks like

The template is the paper version of this inspection. The checks do not change; what changes is that each test point carries its own reading history, a roof installation can raise the bonding question at the time rather than a year later, an operated surge device becomes an open condition, and unbonded additions reach whoever controls access to the roof.

  • Audit Report Intelligence

    Every test point carries its own history

    Readings land against the test point rather than into an annual report, so a connection that has risen across two inspections is flagged while it is still inside the limit instead of at the inspection where it finally fails.

  • Asset Intelligence

    The roof knows what is been added to it

    New plant recorded against the roof raises the bonding question when it is installed, which is the only moment it is cheap, rather than at an inspection months later when it is a defect.

  • Reactive Maintenance Agent

    An operated surge device is an open condition

    A device that has taken a hit becomes a live state on the building rather than a line waiting to be read next year, so spent protection is replaced in weeks instead of months.

  • Work Completion Validator

    Unbonded additions go to roof access, not to electrical

    Because each finding carries where it came from, the count reaches whoever controls permits and handover for the roof, which is where the cause actually sits.

Hallucination-free by design. Atom AI answers from the records in your tenant rather than generating plausible text, so an empty field reads as empty rather than filled in for you.

Frequently asked questions

What should a lightning protection inspection cover?

The air termination network and everything on the roof, the down conductors and their bonds, earth electrodes with resistance readings at each test point, and surge protective devices. It closes with graded defects and a record of roof additions found unbonded.

What distinguishes it from a general electrical inspection is the drawing. The roof is walked against the original design, because the failures that matter are things that are missing rather than things that are faulty.

How often should it be inspected?

Annually is common for a structural system, with the interval set by the design standard, the structure and its exposure, and an additional inspection after any work that could have affected the system or after a known strike.

The interval matters less than keeping the readings together. A system inspected every year by a different contractor, with each report filed separately, produces compliance evidence and no condition information at all.

Why walk the roof against the drawing?

Because the commonest fault is an absence, and absences are invisible without a reference. A bond that was removed during roof works looks like a roof that never had one, and nothing about the installation draws attention to the gap.

It is also how you find additions. Handrails, cradle tracks, condenser frames and solar arrays all get installed by people with no reason to know the system exists, and the drawing is what makes the omission obvious.

Why compare readings instead of just checking the limit?

Because the limit tells you about today and the comparison tells you about next year. A reading that has doubled while staying inside the limit is a connection degrading, and it will be outside the limit at the next inspection.

It costs nothing to do. The reading is being taken anyway; the only requirement is that the previous one is on the same sheet, which is why the template carries a last reading column rather than expecting somebody to find last year is report.

What does an operated surge device mean?

That the building has already taken a transient, the device absorbed it as designed, and the protection it provided is now spent. The device needs replacing, not resetting.

It also means a strike happened that nobody recorded, which is normal on a protected building. The indicator is often the only evidence, which is why reading every one of them is a line on the sheet.

Who is responsible when new roof plant is not bonded?

Functionally, whoever installed it, but practically the problem is upstream of them. Nobody told them the system existed, nobody checked at handover, and the roof access process did not raise it.

That is why the template counts unbonded additions and sends the figure to whoever controls roof access rather than burying it in an electrical report. Fixing the bonds without fixing the process produces the same finding next year.

Does this replace testing by a competent contractor?

No. Resistance testing needs a calibrated instrument and somebody competent to use and interpret it, and the template records the instrument and its calibration for that reason.

What the template adds is the structure around the testing: the comparison with last time, the roof walked against the drawing, and the record of what has been added since, none of which a bare set of readings provides.

Can I edit and rebrand this template?

Yes. It is free to use, edit, rename and put your own logo on, internally or for clients. No attribution required.

The Word version is the one to edit if your design standard or system type differs from the checks as written. The Excel version is the one to use if you want the resistance table with its last reading column and the Test Log tab, which is where the trend becomes visible.

In one paragraph

A lightning protection inspection is mostly a search for things that are no longer there. Start with what has happened on the roof since last time, because new plant, trays, aerials and arrays are installed by people who do not know the system exists. Walk the roof against the original drawing rather than against the roof, since a missing bond looks like a roof that never had one. Open every test joint, because a painted or seized joint was never tested whatever the record says. Take the readings and write last year is figure beside them, since a reading that has doubled inside the limit is a connection that will fail outside it next time. Read the surge indicators, because an operated device means the building has already been struck and is unprotected now. Then report the unbonded additions to whoever controls roof access.

The template is the floor, not the ceiling

Take the template; it will run a proper inspection and leave readings somebody can compare. When a certificate per building stops being enough, a connected CMMS runs the regime: every test point carrying its own reading history so a trend is visible before a failure, roof installations raising the bonding question at the moment they happen, an operated surge device held as a live condition rather than waiting a year to be read, and unbonded additions routed to the process that allowed them.